City of South Miami building permits

City of South Miami issues its own building permits. Their folio numbers start with 09.

Last checked September 22, 2026

How a permit moves through City of South Miami

Where the application starts

More than one way

The City runs an eTRAKiT online permitting portal and also takes submittals at the Building Department’s Permit Desk. Its rule about paper is the one that catches people out: “All forms that are submitted to the Permit Desk must be originals and be notarized.”

Open South Miami eTRAKiT

Source: City of South Miami — Building Permits / Inspections · checked September 22, 2026

Where plans and documents go

More than one way

The City’s instruction is to have two copies of anything accompanying the form — “Make sure you have two copies of any documentation that will be accompanying the form” — which matches its Building Submittal Requirements, where every scope is stated in copies: two of signed and sealed drawings, two of the property survey, two of structural calculations where the plans call for them.

Open South Miami eTRAKiT

Source: City of South Miami — Building Permits / Inspections · checked September 22, 2026

Status and corrections

Online portal

Followed in the eTRAKiT account the permit was filed under; the City publishes an eTRAKiT How To Guide with its forms. For anything the portal does not answer the City names the Building Department directly.

Open South Miami eTRAKiT

Source: City of South Miami — Forms & Applications · checked September 22, 2026

What City of South Miami asks for

City of South Miami publishes submittal requirements for these 15 permit types:

  • New commercial
  • New residential
  • Commercial addition remodel
  • Residential addition remodel
  • Windows doors shutters garage
  • Fence
  • Driveways walkways resurfacing
  • Sheds
  • Demolition
  • Roofing
  • Swimming pools
  • Generator
  • Wood decks
  • Signs
  • Awnings

Fees

City of South Miami’s fee schedule: City of South Miami — Schedule of Fees and Fines, effective The document is headed “As of May 6th, 2026” (The City’s Schedule of Fees and Fines, Building Division section; the document states no adopting ordinance on its face).

Fees are worked out from: New construction, commercial: 2 per cent of the value of construction; New construction, residential: 1.5 per cent of the value of construction; Windows, doors and shutters: 1.5 per cent of the value of construction, capped; Roofing, residential: a rate per square foot; commercial: 2 per cent of the value of construction.

Minimums: Minimum residential permit and minimum commercial permit — recorded as amounts below.

Charged on top: Upfront fee of 30 per cent of the permit fee; Private provider discounts: 40 per cent with plan review and inspections, 25 per cent for inspections only; Reinspection after a second rejected inspection.

Fees are paid to City of South Miami through South Miami online payments.

Official forms

8 forms from City of South Miami’s own forms index. MiamiPermitAI can fill all of them from your project details.

County reviews may also apply: County guide.

Contact

Office
City of South Miami Building Department
Phone
(305) 663-6355
Address
6130 Sunset Drive, South Miami, FL 33143

Source: City of South Miami — Building Submittal Requirements · checked September 19, 2026